Projects

The primary purpose of the May 7th bond was to:

  • enhance safety and security by remodeling and equipping school buildings, playgrounds, and other facilities (including upgrading security cameras, fire alarms, and security film on windows
  • improve energy efficiency with roofing, lighting, and mechanical system replacements
  • update and remodel classrooms and school facilities (including Chatterton Middle School’s Planetarium)
  • upgrade technology and technology infrastructure
  • replace buses as they reach the end of their useful life

Schofield Early Childhood Center

Category                Work Item Description

Environmental         Asbestos abatement

Electrical                   Access control and camera system improvements
                                   Upgrade fire alarm system
                                   Replace building perimeter lighting / Install additional
                                   Generator quick connect
                                   New clock system
                                   New PA system
                                   Technology infrastructure

Exterior                     Replace portion of existing roofing
                                   Replace metal panels above all windows
                                   Replace damaged masonry @ maintenance area

Interior                      Remodel stage area
                                   Replace cabinetry in classrooms
                                   Replace damaged / deteriorated masonry
                                   Replace doors and hardware
                                   Replace basement doors / frames
                                   Install security film on windows
                                   Install window shades on all windows

Mechanical               Replace boiler and pumps
                                   Replace cabinet unit heaters
                                   Replace classroom heat pump units (3 ton)
                                   Replace classroom heat pump units (4 ton)
                                   Replace rooftop heat pump units
                                   Replace circulation pumps for Geothermal System

Site Work                  Install landscaping @ exterior entrance areas
                                   Install fencing around playground areas
                                   Infill grade @ low areas / improve drainage
                                   Replace deteriorated sidewalks
                                   Replace asphalt parking lot
                                   Replace asphalt drop off areas
                                   Replace concrete drive approaches
                                   New directional site signage
                                   Replace digital sign

Technology               Technology equipment – Series #1 & 2

Furnishings               Playground equipment

Westview Lower Elementary School

Category                Work Item Description

Electrical                   Access control and camera system improvements
                                   Upgrade fire alarm system
                                   Replace light poles with LED type
                                   Generator quick connect
                                   New clock system
                                   New PA system
                                   Technology infrastructure

Exterior                     Replace roof in select areas
                                   Replace damaged/deteriorated masonry

Interior                      Remodel damaged terrazzo floor tile
                                   Replace carpeting @ cafeteria stage steps
                                   Replace damaged / deteriorated masonry
                                   Replace restroom flooring/wall covering
                                   Install security film on 1st floor windows

Site Work                  Add fencing around perimeter of playground
                                   Infill grade @ low areas / improve drainage
                                   Replace deteriorated sidewalks
                                   Replace portion of asphalt parking lot
                                   Replace deteriorated areas of parking lot
                                   Install concrete surrounds @ catch basins
                                   New directional site signage
                                   Replace digital sign

Technology               Technology equipment – Series #1 & 2

Furnishings               Playground equipment

Mound Park Upper Elementary School

Category                 Work Item Description

Environmental         Asbestos abatement

Electrical                    Access control and camera system improvements
                                    Replace lighting throughout building
                                    Upgrade fire alarm system
                                    Replace select electrical panels
                                    Replace building perimeter lighting / Install additional
                                    Install parking lot lighting
                                    Generator quick connect
                                    New clock system
                                    New PA system
                                    Technology infrastructure

Exterior                      Replace portion of existing roofing
                                    Replace metal panels above all windows
                                    Replace damaged masonry @ maintenance area

Interior                       Remodel stage area
                                    Replace cabinetry in classrooms
                                    Replace VAT and deteriorated VCT flooring
                                    Replace carpeting in select rooms
                                    Replace ceilings in select rooms
                                    Replace damaged / deteriorated masonry
                                    Replace doors and hardware
                                    Replace hardware at newer doors
                                    Remodel classroom areas at removed mech units
                                    Replace basement doors / frames
                                    Install security film on windows
                                    Install window shades on all windows

Mechanical                Replace boiler and pumps
                                    Remove abandoned mech. units from classrooms
                                    Upgrade condensate drain piping/pans and heat pumps
                                    Replace classroom heat pump units (3 ton)
                                    Replace classroom heat pump units (4 ton)
                                    Replace rooftop heat pump units
                                    Replace rooftop ERV’s
                                    Replace circulation pumps for Geothermal System

Site Work                   Install landscaping @ exterior entrance areas
                                    Infill grade @ low areas / improve drainage
                                    Replace deteriorated sidewalks
                                    Replace concrete porch area (west entry)
                                    Replace asphalt parking lot
                                    Construct dumpster pad
                                    New directional site signage
                                    Replace digital sign

Technology               Technology equipment – Series #1 & 2

Furnishings               Playground equipment

Chatterton Middle School

Category                 Work Item Description

Environmental          Asbestos abatement

Electrical                    Access control and camera system improvements
                                    Upgrade fire alarm system
                                    Replace lighting throughout building
                                    Replace planetarium lighting & sound
                                    Replace select electrical panels
                                    Replace building perimeter lighting / Install additional
                                    Add light poles to SW parking lot
                                    Generator quick connect
                                    New clock system
                                    New PA system
                                    Technology infrastructure

Exterior                      Replace portion of existing roofing
                                    Replace damaged / deteriorated masonry
                                    Replace select exterior doors / frames
                                    Refinish metal panels @ planetarium

Interior                       Remodel old office area & media center
                                    Remodel stage area
                                    Remodel cafeteria
                                    Replace guardrails in cafeteria
                                    Replace cabinetry in classrooms
                                    Replace doors and hardware
                                    Replace ceilings in select areas
                                    Replace flooring in various classrooms with VCT
                                    Replace carpet in media center, choir & misc. offices
                                    Replace damaged / deteriorated masonry
                                    Replace damaged floor tile
                                    Replace corridor lockers
                                    Replace locker room lockers
                                    Scoreboards in gymnasium
                                    Install security film on windows
                                    Install window shades on all windows

Mechanical                Replace gym and locker room HVAC
                                    Replace cafeteria HVAC
                                    Replace media center HVAC
                                    Replace planetarium HVAC

Site Work                   Replace tennis courts
                                     Install landscaping around building perimeter
                                     Infill grade @ low areas / improve drainage
                                     Replace asphalt parking lot
                                     Replace deteriorated sidewalks
                                     Scoreboards @ baseball / softball fields
                                     New directional site signage
                                      Replace digital sign

Technology                 Technology equipment – Series # & 2

Furniture                     Replace planetarium equipment
                                      New furnishings

Fitzgerald High School

Category                Work Item Description

Addition                    Construct weight room addition

Environmental          Asbestos abatement – Series #1 & 2

Electrical                    Access control and camera system improvements
                                    Upgrade fire alarm system
                                    Replace select electrical panels
                                    Replace building perimeter lighting / Install additional
                                    New clock system
                                    New PA system
                                    Technology infrastructure

Exterior                      Remodel exterior entrance to auditorium
                                    Replace portion of existing roofing
                                    Replace damaged / deteriorated masonry
                                    Replace flashing @ band rm windows

Interior                      Remodel interior space of auditorium lobby
                                    Remodel auditorium stage (including circular stairs),                                                   auditorium lighting and sound
                                    Remodel interior space of auditorium
                                    Replace auditorium seating
                                    Remodel office space into 9th grade classrooms
                                    Remodel media center into flexible learning space
                                    Replace cabinetry in classrooms
                                    Replace VAT and deteriorated VCT flooring
                                    Replace ceilings in select areas
                                    Replace damaged / deteriorated masonry
                                    Replace doors and hardware
                                    Replace walk off mats at entries
                                    Re-grout pool
                                    Replace doors in pool area
                                    Scoreboards in Gymnasiums
                                    Install security film on 1st floor windows
                                    Install window shades on all windows

Mechanical                Replace pool HVAC equipment & ductwork
                                    Replace air handling unit serving pool locker rooms
                                    Replace auditorium chiller compressor
                                    Replace recirculation pump & chemical feeder for pool

Site Work                   Replace portion of asphalt parking lot
                                    Replace deteriorated sidewalks
                                    Replace damaged concrete curbs
                                    Landscaping improvements
                                    Scoreboard @ football field
                                    New directional site signage
                                    Replace digital sign

Technology                Technology equipment – Series #1& 2