Schofield Early Childhood Center
Category Work Item Description
Environmental Asbestos abatement
Electrical Access control and camera system improvements
Upgrade fire alarm system
Replace building perimeter lighting / Install additional
Generator quick connect
New clock system
New PA system
Technology infrastructure
Exterior Replace portion of existing roofing
Replace metal panels above all windows
Replace damaged masonry @ maintenance area
Interior Remodel stage area
Replace cabinetry in classrooms
Replace damaged / deteriorated masonry
Replace doors and hardware
Replace basement doors / frames
Install security film on windows
Install window shades on all windows
Mechanical Replace boiler and pumps
Replace cabinet unit heaters
Replace classroom heat pump units (3 ton)
Replace classroom heat pump units (4 ton)
Replace rooftop heat pump units
Replace circulation pumps for Geothermal System
Site Work Install landscaping @ exterior entrance areas
Install fencing around playground areas
Infill grade @ low areas / improve drainage
Replace deteriorated sidewalks
Replace asphalt parking lot
Replace asphalt drop off areas
Replace concrete drive approaches
New directional site signage
Replace digital sign
Technology Technology equipment – Series #1 & 2
Furnishings Playground equipment
Westview Lower Elementary School
Category Work Item Description
Electrical Access control and camera system improvements
Upgrade fire alarm system
Replace light poles with LED type
Generator quick connect
New clock system
New PA system
Technology infrastructure
Exterior Replace roof in select areas
Replace damaged/deteriorated masonry
Interior Remodel damaged terrazzo floor tile
Replace carpeting @ cafeteria stage steps
Replace damaged / deteriorated masonry
Replace restroom flooring/wall covering
Install security film on 1st floor windows
Site Work Add fencing around perimeter of playground
Infill grade @ low areas / improve drainage
Replace deteriorated sidewalks
Replace portion of asphalt parking lot
Replace deteriorated areas of parking lot
Install concrete surrounds @ catch basins
New directional site signage
Replace digital sign
Technology Technology equipment – Series #1 & 2
Furnishings Playground equipment
Mound Park Upper Elementary School
Category Work Item Description
Environmental Asbestos abatement
Electrical Access control and camera system improvements
Replace lighting throughout building
Upgrade fire alarm system
Replace select electrical panels
Replace building perimeter lighting / Install additional
Install parking lot lighting
Generator quick connect
New clock system
New PA system
Technology infrastructure
Exterior Replace portion of existing roofing
Replace metal panels above all windows
Replace damaged masonry @ maintenance area
Interior Remodel stage area
Replace cabinetry in classrooms
Replace VAT and deteriorated VCT flooring
Replace carpeting in select rooms
Replace ceilings in select rooms
Replace damaged / deteriorated masonry
Replace doors and hardware
Replace hardware at newer doors
Remodel classroom areas at removed mech units
Replace basement doors / frames
Install security film on windows
Install window shades on all windows
Mechanical Replace boiler and pumps
Remove abandoned mech. units from classrooms
Upgrade condensate drain piping/pans and heat pumps
Replace classroom heat pump units (3 ton)
Replace classroom heat pump units (4 ton)
Replace rooftop heat pump units
Replace rooftop ERV’s
Replace circulation pumps for Geothermal System
Site Work Install landscaping @ exterior entrance areas
Infill grade @ low areas / improve drainage
Replace deteriorated sidewalks
Replace concrete porch area (west entry)
Replace asphalt parking lot
Construct dumpster pad
New directional site signage
Replace digital sign
Technology Technology equipment – Series #1 & 2
Furnishings Playground equipment
Chatterton Middle School
Category Work Item Description
Environmental Asbestos abatement
Electrical Access control and camera system improvements
Upgrade fire alarm system
Replace lighting throughout building
Replace planetarium lighting & sound
Replace select electrical panels
Replace building perimeter lighting / Install additional
Add light poles to SW parking lot
Generator quick connect
New clock system
New PA system
Technology infrastructure
Exterior Replace portion of existing roofing
Replace damaged / deteriorated masonry
Replace select exterior doors / frames
Refinish metal panels @ planetarium
Interior Remodel old office area & media center
Remodel stage area
Remodel cafeteria
Replace guardrails in cafeteria
Replace cabinetry in classrooms
Replace doors and hardware
Replace ceilings in select areas
Replace flooring in various classrooms with VCT
Replace carpet in media center, choir & misc. offices
Replace damaged / deteriorated masonry
Replace damaged floor tile
Replace corridor lockers
Replace locker room lockers
Scoreboards in gymnasium
Install security film on windows
Install window shades on all windows
Mechanical Replace gym and locker room HVAC
Replace cafeteria HVAC
Replace media center HVAC
Replace planetarium HVAC
Site Work Replace tennis courts
Install landscaping around building perimeter
Infill grade @ low areas / improve drainage
Replace asphalt parking lot
Replace deteriorated sidewalks
Scoreboards @ baseball / softball fields
New directional site signage
Replace digital sign
Technology Technology equipment – Series # & 2
Furniture Replace planetarium equipment
New furnishings
Fitzgerald High School
Category Work Item Description
Addition Construct weight room addition
Environmental Asbestos abatement – Series #1 & 2
Electrical Access control and camera system improvements
Upgrade fire alarm system
Replace select electrical panels
Replace building perimeter lighting / Install additional
New clock system
New PA system
Technology infrastructure
Exterior Remodel exterior entrance to auditorium
Replace portion of existing roofing
Replace damaged / deteriorated masonry
Replace flashing @ band rm windows
Interior Remodel interior space of auditorium lobby
Remodel auditorium stage (including circular stairs), auditorium lighting and sound
Remodel interior space of auditorium
Replace auditorium seating
Remodel office space into 9th grade classrooms
Remodel media center into flexible learning space
Replace cabinetry in classrooms
Replace VAT and deteriorated VCT flooring
Replace ceilings in select areas
Replace damaged / deteriorated masonry
Replace doors and hardware
Replace walk off mats at entries
Re-grout pool
Replace doors in pool area
Scoreboards in Gymnasiums
Install security film on 1st floor windows
Install window shades on all windows
Mechanical Replace pool HVAC equipment & ductwork
Replace air handling unit serving pool locker rooms
Replace auditorium chiller compressor
Replace recirculation pump & chemical feeder for pool
Site Work Replace portion of asphalt parking lot
Replace deteriorated sidewalks
Replace damaged concrete curbs
Landscaping improvements
Scoreboard @ football field
New directional site signage
Replace digital sign
Technology Technology equipment – Series #1& 2
Furniture New furnishings – Series #2 & 3